Xcel Energy is preparing to start transmission line construction on its Northern Colorado Area Plan (NCAP). The project website, xcelenergynortherncoloradoareaplan.com will be updated regularly with the latest construction and schedule details.
If you have questions, concerns, or want to schedule a meeting, contact Xcel at 888.678.7640 or NorthernColorado@XcelEnergy.com.
The current schedule of construction work is as follows:
- Feb-March: Installing foundation at the new Husky Substation at 16387 Highland Street in Ault
- March: Begin construction on the 230-kV WAPA Ault to Husky transmission line
- April: Begin construction on the new Collins Street Substation in the Town of Eaton